An EICR (Electrical Installation Condition Report) is the report an electrician gives you after inspecting and testing the fixed wiring in a home. For a landlord in England, the law says you need one at least every five years, you must give a copy to your tenants, and any dangerous faults it finds must be fixed within 28 days. This guide explains the EICR landlord rules in plain English, including what the codes on the report mean.

This applies to England. Wales, Scotland and Northern Ireland have different rules.

EICR landlord rules: what the 2020 Regulations require

The rules are in the Electrical Safety Standards in the Private Rented Sector (England) Regulations 2020. Regulation 3 came into force on 1 June 2020. "Fixed wiring" means the electrics built into the home: the fuse box, sockets, switches, light fittings and the cables behind the walls.

Under regulation 3, a landlord must:

  • make sure the electrical safety standards are met while the home is let;
  • have the wiring inspected and tested at least every five years, or sooner if the last report says so;
  • get a written report from the person who did it, showing the results and the date of the next inspection;
  • give copies of the report to tenants and the council on time (see below);
  • keep a copy until the next inspection is due;
  • get any repairs or further checks the report asks for done by a qualified person within 28 days, or sooner if the report says so.

The rules were extended to social landlords in 2025. The current government guidance, published on 1 November 2025, covers both private and social renting.

Which lets are left out

The same guidance lists lets that are not covered, including:

  • lodgers who share the home with the landlord or their family;
  • long leases, or tenancies of seven years or more;
  • student halls of residence;
  • hostels and refuges;
  • care homes, hospitals and hospices;
  • mobile homes, caravans and boats.

An ordinary flat or house on a private tenancy is covered.

Do you need a new EICR for each tenancy?

No. The guidance says there's no need for another inspection before re-letting, as long as you have a report less than five years old that doesn't ask for more work. You must still give the new tenant a copy. A quick look over the sockets and fittings between tenants is a good idea anyway.

Who can do an EICR

The regulations say the inspection must be done by someone "competent" to do it. They don't name one qualification. The government guidance points landlords to the Electrical Safety Roundtable guidance, the Registered Competent Person Electrical register, and Electrical Safety First's "find a registered electrician" tool.

In practice, check three things before you book:

  1. The electrician is on a recognised register.
  2. They do periodic inspection and testing, not just installation work.
  3. They carry suitable insurance.

EICR codes C1, C2, C3 and FI explained

The report grades each problem with a code. The standard it checks against is British Standard 7671 (the "Wiring Regulations"). Here's what each code means, using the wording from the government guidance:

Code What it means What you must do
C1 "Danger present. Risk of injury." Fix within 28 days, or sooner if the report says. The electrician may make it safe before they leave.
C2 "Potentially dangerous." Fix within 28 days, or sooner if the report says.
C3 "Improvement recommended." No legal duty to act. Worth planning in.
FI "Further investigation required without delay." Get the investigation done within 28 days, or sooner if the report says.

If a report has any C1 or C2 codes, it will say the installation is "unsatisfactory for continued use". That's what people mean by a "failed" EICR.

Example

Say your electrician visits on 3 March 2027. The report has one C2 (a socket with signs of overheating) and two C3s (older-style fittings).

  • The report is unsatisfactory because of the C2.
  • The socket must be fixed by a qualified person by 31 March 2027 (28 days), unless the report gives a shorter date.
  • Once it's fixed, you get written confirmation of the work.
  • The C3s don't need doing by law. You might add them to the landlord's list for the next empty period.

Remedial work deadlines

"Remedial work" just means repairs. The regulations give you 28 days (or less, if the report says so) but don't spell out the exact start day. To be safe, count from the date of the inspection, not the day you get round to reading the report. So ask the electrician to send the report quickly and to quote for repairs at the same time.

Once the repairs or investigation are done, regulation 3 says you must get written confirmation from the electrician that the work is complete and the standards are met. You must give that confirmation, with the original report, to the tenant and the council within 28 days of the work being finished.

If an FI investigation finds more problems, the same steps start again for the new work.

"Reasonable steps"

Regulation 3 says a landlord isn't in breach if they can show they took all reasonable steps to comply. A common example is a tenant who won't let the electrician in. Keep a dated record of every attempt to book the visit. That record is what protects you.

Giving copies of the EICR to tenants and councils

Regulation 3 sets out who gets a copy and when:

Who When
Current tenants Within 28 days of the inspection
New tenants Before they move in
Someone thinking of renting (if they ask in writing) Within 28 days of their request
The council (if it asks in writing) Within 7 days of its request
The electrician who does the next inspection When they do it

The seven-day council deadline is the one most likely to catch you out. It's much easier to meet if every report sits on the property file, not in someone's inbox.

Penalties

Councils enforce these rules. If a landlord doesn't do repairs, the council can serve a remedial notice and, in urgent cases, arrange the work itself and recover the cost.

The council can also charge a fine called a financial penalty. Under regulation 11 as it reads today, the maximum is £40,000. That figure was put in by S.I. 2025/1043, which took effect on 1 November 2025 for some purposes and 1 May 2026 for the rest. The government guidance also says councils "may impose a financial penalty of up to £40,000". Older articles may quote a lower figure, so check the date on anything you read.

Tracking EICR renewal dates

Five years is long enough to forget. By the time an EICR is due, the property manager who booked the last one may have left. So treat the date as data, not memory.

Here's what to record for each property:

  • the inspection date and the next due date printed on the report (this can be shorter than five years);
  • whether the report was satisfactory or not;
  • each C1, C2 and FI item, the repair date and the written confirmation;
  • when and how each tenant got their copy.

Software helps here because the deadlines overlap. Fivura holds each property's certificates on its compliance record and sends reminders to your team and the landlord 30, 14, 7 and 1 day before a certificate runs out, and again once it has. Gas safety works the same way, so see our guide to the landlord gas safety certificate. For every other certificate, use our landlord compliance checklist.

Related guides: Right to Rent Checks, Landlord Certificate Reminders.

Frequently asked questions

How often does a landlord need an EICR?

At least every five years. The Electrical Safety Standards in the Private Rented Sector (England) Regulations 2020 say the wiring must be inspected and tested at intervals of no more than five years. If the last report asks for an earlier check, for example after three years, you must follow the shorter date instead. You don't need a new report just because the tenant changes.

Yes, for most private lets in England. The 2020 Regulations have applied to private landlords since 1 June 2020. Some lets are left out, such as lodgers who share with the landlord, long leases of seven years or more, student halls and hostels. Social landlords were brought in from 1 November 2025, for tenancies granted after 1 December 2025, and from 1 May 2026 for older ones.

What does C2 mean on an EICR?

C2 means "potentially dangerous". It isn't an emergency yet, but it could become one. The government guidance says that a C1 or C2 on the report means remedial work is needed and the installation is "unsatisfactory for continued use". You must get the work done by a qualified person within 28 days, or sooner if the report says so.

Do I need a new EICR for every new tenancy?

No. The government guidance says there's no need for a fresh inspection before re-letting, as long as you have a report less than five years old that doesn't ask for further work. You must give the new tenant a copy of that report before they move in. A quick visual check of sockets and fittings between tenants is still a good idea.

Stay ahead of every renewal

Track every certificate and expiry in one place: try Fivura's compliance tracking.


How we wrote this: on 4 November 2026 we checked the Electrical Safety Standards in the Private Rented Sector (England) Regulations 2020 (regulations 3 and 11, as amended) on legislation.gov.uk and the government's November 2025 guidance on gov.uk. The Fivura Editorial Team wrote this guide. No lawyer has reviewed it.

This guide is general information, not legal or tax advice. Check the official guidance linked above or speak to a qualified adviser.